    Update on Dam repair report!

    This from LC.com

    Wolf Creek Dam project is right on schedule


    By BILL MARDIS, Someret Commonwealth Journal

    A construction update this week from Wolf Creek Dam indicates rehabilitation of the mile-long structure is on schedule and progressing as planned for completion in three years.

    Allison Jarrett, public affairs specialist for the U.S. Army Corps of Engineers, said Treviicos Soletanche JV, general contractor for the project, has completed installation of the last panels of the protective concrete embankment wall in Technique Areas 1 and 2. The two technique areas are test spots to confirm integrity of the process to stop uncontrolled seepage through the dam that has been declared in high risk of failure.

    The protective concrete embankment wall in its entirety consists of 427 concrete panels, 6 feet wide and 10 feet long, to stabilize the earthen section of the dam while a permanent barrier wall is installed.

    The protective concrete embankment wall will extend from the work platform on the upstream side of the dam downward to the base of the earthen section. This wall, as well as an original wall installed in the 1970s, will remain in the dam to augment the permanent barrier wall that will extend as much as 100 feet into the bedrock below the dam. The permanent wall is scheduled for completion in October 2012.

    The original wall, installed after more serious leaks developed in the dam during the late 1960s, was not long enough or deep enough to permanently repair the dam. The first wall extended only about 25 feet into the bedrock below the dam and stopped short of protecting the entire length of the structure. Seepage increased to the point that an outside panel of experts declared the structure in high risk of failure. The Corps announced publicly in August 2005 that a major rehabilitation of the dam was necessary.

    Jarrett said this week that subcontractor Hayward Baker has grouted 100 primary and secondary holes along the right rim near Halcomb’s Landing. Testing results indicate 94 tertiary (third) holes will be required to meet closure criteria (about 75 percent of these tertiaries are completed). She said Hayward Baker has completed grouting large cavities in Critical Area 1 and has begun grouting the rock beneath.

    A really troublesome spot is Critical Area 1 near where the earthen and concrete sections of the dam join. Original efforts to pump high-mobility (thin) grout into the critical area increased seepage and there was indication of material movement inside the dam.

    Grouting was halted, resulting in an incomplete grout curtain to temporarily control seepage. The problem delayed any consideration of raising the lake level until October 2010, meaning the lake will remain at its current level through next summer.

    CLIC

  2. #2
    Join Date
    Dec 1969
    Location
    .Taylor Mill Ky.
    Posts
    604
    Post Thanks / Like

    Re: Update on Dam repair report!


  3. #3
    Join Date
    Dec 1969
    Location
    .Taylor Mill Ky.
    Posts
    604
    Post Thanks / Like

    Re: Update on Dam repair report!

    Dam project pushed back


    Commonwealth Journal - Somerset — Problems with directional drilling of pilot holes have delayed work at Wolf Creek Dam and pushed back the projected completion of the dam rehabilitation project to December 2012, about two months later than the contract deadline.

    David Hendrix, project manager for the $584 million repair project, said the delay also will mean evaluation of the level of Lake Cumberland won’t be done at least until December 2010, about two months later than projected. Engineers said earlier when the permanent wall has been installed in two critical areas of the dam by next October the current lake level could be evaluated.

    Tourism interests around Lake Cumberland have been clinging to the October 2010 evaluation of the dam repair progress that might allow the level of Lake Cumberland to be raised, hopefully 10 feet, for the 2011 vacation season.

    Despite the projected delay, Hendrix didn’t rule out the possibility of a higher lake level during summer 2011. “Even if we could make the evaluation as late as March (2011) spring rains could allow a change in the lake level,” he said.

    Problems with drilling pilot holes, 8 inches in diameter, have caused the delay, Hendrix explained. The pilot holes are guides for 50-inch circular shafts that will be backfilled with concrete to form the permanent barrier wall. Three of the large holes have been completed in Technique Area 1, one of two test areas to determine integrity of the work, Hendrix noted.
    CLICK HERE FOR FULL STORY

Similar Threads

  1. HDS 4.0 Update
    By E-TECH 200 in forum Indiana Discussion Board
    Replies: 6
    Last Post: 05-12-2011, 04:29 PM
  2. Jan 19 update report
    By PRO V LE in forum Kentucky Discussion Board
    Replies: 1
    Last Post: 03-11-2011, 04:28 PM
  3. Need Update for the HDS 8
    By Castin_A_Jig in forum Classifieds for Individuals (FREE)
    Replies: 1
    Last Post: 01-15-2010, 12:32 PM
  4. Tnt update
    By TOURNEYS in forum Kentucky Fishing Tournaments
    Replies: 0
    Last Post: 04-08-2009, 09:23 PM
  5. Cumberland Dam Repair Update
    By fishbum in forum Kentucky Discussion Board
    Replies: 0
    Last Post: 03-17-2006, 05:17 PM

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •