Search Fishin.com

Results 1 to 5 of 5

Hybrid View

  1. #1
    Join Date
    Dec 1969
    Location
    .Taylor Mill Ky.
    Posts
    604
    Post Thanks / Like

    June 25/2011 update

    June 24, 2011 Corps makes dam work go easier


    by Bill Mardis Commonwealth Journal

    Somerset —
    The U.S. Army Corps of Engineers will make it easier for contractors to work in the most critical area of leak-plagued Wolf Creek Dam.
    Lee Roberts, public affairs specialist for the Corps’ Nashville District, said a lower access road and higher work platform are planned to facilitate contractors’ operations at the critical spot where the earthen section wraps around the concrete monolith.
    “We are waiting on these actions as we continue to draw down the lake level,” Roberts said. The lake, flushed by heavy spring rains, is falling 3 to 5 inches a day and is still about 10 feet above the optimum 680 feet above sea level. The lake has been held as close as possible to 40 feet below pool stage to ease pressure on the troubled structure and facilitate the ongoing rehabilitation project.
    Roberts indicated the planned access road will be built between the electrical grid at the downriver base of the dam and tailwaters of the Cumberland River immediately below the dam. The new road apparently is necessary to bring heavy equipment up the incline to the work site.
    The higher platform will make it easier for contractors to work in the extremely fragile area. This section of the work platform will be elevated from the existing platform built on the upstream side of the dam at the start of the rehabilitation project.
    Drilling in the critical area, where work has been stopped for almost a year, resumed June 1. Vertical holes are being drilled to define edges of the cave and core trench along alignment of a proposed concrete barrier wall. After testing, the holes will be gravity backfilled with grout (chemically treated liquid concrete) to enable safe installation of the barrier wall.
    The Corps scrapped plans to drill in Critical Area 1 through specially designed double-walled steel casings to protect the integrity of the dam in this cavern-laced area. Instead, they have decided to use existing equipment and techniques to install the permanent concrete barrier wall.
    At last report, the total rehabilitation project of Wolf Creek Dam is slightly more than 50 percent complete. A permanent concrete barrier wall, longer and deeper than a similar wall inserted during the 1970s, is being built in the earthen section of the dam. The wall is created by drilling overlapping 50-inch-diameter holes filled with concrete.
    Wolf Creek Dam has been plagued by seepage since the gates were closed in December 1950. The dam was classified in high risk of failure in 2005 and a $584 million rehabilitation of the structure began in 2007. Latest projections are the project will be completed in December 2013

  2. #2
    Join Date
    Nov 2006
    Location
    KY
    Posts
    2,127
    Post Thanks / Like

    Re: June 25/2011 update

    Thanks for the update.

  3. #3
    Join Date
    Apr 2011
    Posts
    27
    Post Thanks / Like

    Re: June 25/2011 update

    Man they need to hurry up, juss sayin haha

  4. #4
    Join Date
    Oct 2009
    Location
    eastview, ky
    Posts
    1,122
    Post Thanks / Like

    Re: June 25/2011 update

    Wonder how long before it starts to leak again?

  5. #5
    Join Date
    Dec 1969
    Location
    NKY
    Posts
    352
    Post Thanks / Like

    Re: June 25/2011 update

    It took em over a year to figure out plan B which is just a beefed up copy of the fix from 1970s? How do I get on that payroll....

Similar Threads

  1. C-River 10-14 June
    By 410th in forum Kentucky Discussion Board
    Replies: 6
    Last Post: 06-15-2011, 10:49 PM
  2. 5 June 2011 Crappie Tournament
    By lukepittman in forum Indiana Fishing Tournaments
    Replies: 2
    Last Post: 05-26-2011, 05:11 PM
  3. Coe, jan 12, 2011 update
    By FlyLie in forum Kentucky Discussion Board
    Replies: 1
    Last Post: 01-17-2011, 06:05 PM
  4. June Ups & Downs
    By TheBEAST in forum Florida Discussion Board
    Replies: 0
    Last Post: 06-28-2008, 11:43 PM
  5. CH - Thursday, 7 June
    By Dover in forum Tennessee Discussion Board
    Replies: 1
    Last Post: 06-13-2007, 01:57 AM

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •